09/06/08 Frank Mazza And The Band Of Idiot's Breakdown from the money discussed at the Hamilton Avenue School Building Committee



YOU WONT READ THIS IN THE GREENWICH TIME, BECAUSE THEY HAVE THEIR HEADS IN THE SAND



Breakdown from the money discussed
at the Hamilton Avenue School
Building Committee Meeting
The Building Committee's $700,000 
interim request breaks down as follows:  
 
$296,753 for change order request either completed or underway; 
$36,000 to install insulation in the old attic; 
$49,000 to install differential pumps 
to ensure that that the heat pumps work properly; 
$50,000 to cap the chimneys 
that Worth Construction wont pay for, 
$30,000 for the project management fees; 
$125,000 for additional work required to
complete the school???????; 
and a $100,000 contingency that will spent!!!!! 
Frank Mazza will be presenting this new information 



Please send your comments to GreenwichRoundup@gmail.com