YOU WONT READ THIS IN THE GREENWICH TIME, BECAUSE THEY HAVE THEIR HEADS IN THE SAND
Breakdown from the money discussed
at the Hamilton Avenue School
Building Committee Meeting
The Building Committee's $700,000
interim request breaks down as follows:
$296,753 for change order request either completed or underway;
$36,000 to install insulation in the old attic;
$49,000 to install differential pumps
to ensure that that the heat pumps work properly;
$50,000 to cap the chimneys
that Worth Construction wont pay for,
$30,000 for the project management fees;
$125,000 for additional work required to
complete the school???????;
and a $100,000 contingency that will spent!!!!!
Frank Mazza will be presenting this new information
to the BET on Monday 09/08/08.
PLEASE ALSO SEE:
09/01/08 Why Are Betty Sternberg, Susan Wallerstein And Anthony Byrne Still Collecting Board Of Education Paychecks????
08/29/08 Is Michael Bodson Parading Colin Gustafson With A Nose Ring?
Please send your comments to GreenwichRoundup@gmail.com
No comments:
Post a Comment
Useful criticism, helpful links and corrections and general comments are always welcome at Greenwich Roundup. Generally only spam ads and posts with very foul language get censored.
Contact me directly at GreenwichRoundup@gmail.com if you have a suggestion or comment you don't want publicized (but tell me so in your email).
I look forward to publishing your opinions.
COMMENTING RULES: We encourage an open exchange of ideas in the Greenwich community, but we ask you to follow our guidelines. Basically, be civil, smart, on-topic and free from profanity. Don't say anything you wouldn't want your mother to read!